|
Master Plan Update: Land
planning phase |
|
Parishioners were
relieved and pleased a few months back with the amicable settlement with
our neighbors and the borough regarding the development of several
nearby properties for Church use. We also noticed, quite
dramatically, the process and impact of the December demolition of the
three older buildings that would not be used by St. Patrick, clearing
the way for the new — in accordance with the parish development plan.
Development progress has not been nearly as obvious in the past several
weeks, however, perhaps causing some to wonder if a financial or
logistical snag had been encountered. This is not the case;
indeed, our Property and Development Committee has been very involved in
the current “land planning phase” of the project, and things are well on
track.
Evaluation of soil samples is currently underway. One requirement
is to look for hazardous components in the soil, but these are not
expected on this site — based upon earlier test results. More important,
at this point in time, is the “perc” (percolation) testing needed for
the engineering of a water management plan — taking into account the
physical characteristics of the soil and terrain. In particular,
water runoff needs must be anticipated, and provisions must be made that
take into account the entire scope of the project. As this will be
impacted directly by the evolving facilities footprint, and especially
pavement coverage, data and time are required for the relevant civil
engineering considerations. This process is normal — it is
typically part of any substantial new building project.
The area traffic study is also being completed. Combining the
outcomes of these efforts, application for integrated project approval
will be submitted to the Kennett Square Planning Commission no later
than March 15th. Jim Elliott of the Properties and Development
Committee reports that these activities are moving in parallel, and on
track with schedule. Following submittal, he expects that several
weeks will be required for assessment and approval.
Committee member Tom Fero adds that with the momentum gained from our
settlement last fall, continued planning discussions with Kennett Square
officials have remained very positive and amicable throughout this
phase. This is one of the most critical considerations going
forward, including maintenance of timely and accurate communications
with the borough, and our neighbors.
In addition to Jim and Tom, Property and Development Committee members
include Drew Anderson, Chris Claudy, Jerry Kane, Mike Miller, Marge
Mecca and Father Sharrett. Mike functions as the “point man” with
Bernardon & Associates, actively refining details of the internal
building modifications coming in future phases.
Bernardon, in turn, continues in its contracted role as our professional
architectural and engineering resource, overseeing the full project
effort. For the current engineering studies, they have
subcontracted Gilmore & Associates for this specific expertise.
Our near term goal is to obtain the “go ahead” for needed lighting and
telephone improvements for 205 Lafayette Street, which will soon serve
as our parish office.
The office move will immediately free up space for the planned near-term
expansion of school offerings. Expected activities this summer
include movement of the school library to the present office building on
Meredith Street, followed by transition of the existing library space to
kindergarten and pre-K facilities. This facilitates the
introduction of the full-day kindergarten option, as well as three and
four-year old pre-K offerings. The current expectation is that all
of this will be in place for the start of school this fall.
St. Pat's Today. March 2005.
|
|